MANTRA 2002 Schedule
MILESTONE
|
NOMINAL DATE
|
Requirements
Review
|
January
24, 2002
|
Start
of CSA/NSERC support
|
February
2002
|
Critical
Design Review
|
April
18, 2002
|
SIL
to send gondola, CIP, etc. to U of Toronto
|
June
10, 2002
|
Flight
Readiness Review
|
June
20, 2002
|
All
instruments to U of T for integration
|
July 2002
|
Ship
to Vanscoy
|
August
8, 2002 arrive by August 12
|
Sondes
and ground-based measurements start
|
August
13, 2002
|
Science
team arrival at Vanscoy
|
August
13-17, 2002
|
On
site payload integration
|
August
16 - September 3, 2002
|
Flight
ready, awaiting good winds and weather
|
August
31, 2002
|
Balloon launch
|
2:02 AM LT (8:02 UTC), Sept. 3
|
Post-Flight Review Meeting
|
October
2, 2002
|
Post-Flight Report
|
November
4, 2002
|
First
Data Workshop
|
November
25, 2002
|
Second
Data Workshop
|
June
15, 2003
|
|